The Fashion Retail Calendar
Fashion retail operates on a predictable calendar with specific windows for each season. Understanding these windows is essential for logistics timing.
Major Retail Seasons
| Season | Floor Set | Peak Selling | Markdown Start |
|---|---|---|---|
| Spring | February | March-April | May |
| Summer | May | June-July | August |
| Fall | August | September-October | November |
| Holiday | October | November-December | December 26 |
| Resort/Cruise | November | December-January | January |
Key Retail Events
- President's Day (February): Spring promotional kickoff
- Memorial Day (May): Summer season launch
- Back to School (August): Major volume driver
- Labor Day (September): Fall promotional event
- Black Friday/Cyber Monday (November): Holiday peak
Retail Lead Time Requirements
Retailers need product in their DCs before floor set dates:
- Department stores: 4-6 weeks before floor set
- Specialty retail: 2-4 weeks before floor set
- E-commerce: 1-2 weeks before launch
Production Timeline Planning
Working backward from retail floor sets, production and logistics timelines determine when design must be finalized and production must begin.
Spring/Summer Timeline
| Milestone | Timing |
|---|---|
| Design finalization | June-July (prior year) |
| Production start | August-September |
| Production complete | October-November |
| Ship from origin | November-December |
| Arrive at retailer DC | January |
| Floor set | February |
Fall/Winter Timeline
| Milestone | Timing |
|---|---|
| Design finalization | December-January |
| Production start | February-March |
| Production complete | April-May |
| Ship from origin | May-June |
| Arrive at retailer DC | June-July |
| Floor set | August |
Holiday Timeline (Critical)
Holiday has the most compressed and high-stakes timeline:
- Design finalization: February-March
- Production complete: July-August
- Ship from origin: August (critical deadline)
- Arrive at retailer: September-October
- Floor set: October
Missing the August ship deadline often means either expensive air freight or missing the holiday season entirely.
Want to see how Cubic compares to your current forwarder?
Logistics Timing Considerations
Logistics lead times must be built into production planning. Ocean freight especially requires significant buffer.
Ocean Transit Times
| Origin | To West Coast | To East Coast |
|---|---|---|
| China/Vietnam | 14-21 days | 28-35 days |
| Bangladesh/India | 25-35 days | 20-28 days |
| Turkey | 35-42 days | 18-25 days |
Beyond Transit Time
Total logistics lead time includes:
- Booking to vessel: 1-2 weeks
- Ocean transit: 2-5 weeks
- Port dwell and customs: 3-7 days
- Inland transport to DC: 3-10 days
- DC receiving and processing: 3-7 days
Total: 4-8 weeks from factory door to retailer DC
Peak Season Considerations
Add buffer for peak shipping seasons:
- August-October: Peak ocean freight season, add 1-2 weeks
- Chinese New Year: Factory closures require 2-4 week buffer
- Blank sailings: Carriers may skip ports, extending transit
Port and Customs Delays
Build contingency for:
- Port congestion (common at West Coast ports)
- Customs examinations (textile verification, UFLPA holds)
- Documentation issues
- Weather-related delays
Managing Seasonal Inventory Flow
Multiple seasons overlap in production and delivery. Managing flow prevents warehouse overload and ensures clean transitions.
Seasonal Overlap Pattern
At any given time, multiple seasons are active:
- In stores: Current season selling
- In transit: Next season shipping
- In production: Season after next in production
- In design: Two seasons ahead in development
Warehouse Capacity Planning
Peak warehouse load typically occurs when:
- Current season clearance inventory remains
- Next season pre-positioned inventory arrives
- Overlap can exceed 150% of single-season capacity
Flow Strategies
- Flow-through processing: Move new season direct to stores, reducing DC inventory
- Staggered receipts: Schedule deliveries to flatten peak
- External overflow: Contract warehouse space for peak periods
- Returns processing: Clear previous season returns before new season arrives
Transition Timing
Critical transitions requiring careful planning:
- Winter to Spring: February—heavy outerwear exits, lighter goods arrive
- Summer to Fall: August—back-to-school plus fall basics
- Fall to Holiday: October—gift items layer on top of fall
Weather and Seasonal Shifts
Climate patterns affect when consumers buy seasonal products. Planning must account for regional differences and weather volatility.
Regional Timing Differences
Seasonal needs vary by geography:
- Sunbelt: Lighter spring/summer focus, less outerwear
- Northeast/Midwest: Strong seasonal swing, heavy outerwear
- Pacific Northwest: Rain gear focus, less extreme cold
Weather-Responsive Inventory
- Core seasonal: Buy based on historical patterns
- Weather-sensitive: Hold inventory for weather-triggered shipments
- Warm weather contingency: Plans if winter is mild (push outerwear promotions)
- Cold snap response: Rapid replenishment when cold arrives
Climate Trend Impacts
Longer-term climate patterns are shifting seasons:
- Earlier spring warmth pushing summer buying earlier
- Later fall cold delaying outerwear sales
- More volatile weather creating demand spikes
Planning Implications
- Consider regional floor sets vs. national timing
- Build flexibility to accelerate or delay shipments
- Pre-position inventory closer to demand for faster response
- Develop rapid-response capabilities for weather-driven demand
Chinese New Year Planning
Chinese New Year (CNY) shuts down Asian manufacturing for 2-4 weeks. This creates a critical planning constraint for spring production.
CNY Impact
- Factory closure: 7-14 days official, often 3-4 weeks effective
- Pre-CNY rush: Factories push to complete orders, quality may suffer
- Post-CNY ramp-up: Worker return rates uncertain, 2-3 weeks to full capacity
- Total disruption: 4-6 weeks of affected production
CNY Dates
CNY falls between late January and mid-February (varies by lunar calendar):
- 2025: January 29
- 2026: February 17
- 2027: February 6
Planning Strategies
- Complete before CNY: Ship Spring product before factories close (preferred)
- Resume after CNY: Accept late February/March delivery (risky for spring floor sets)
- Pre-position fabric: Have materials ready to cut immediately post-CNY
- Non-China production: Use factories in countries without CNY impact
Shipping During CNY
Even if production completes before CNY:
- Freight forwarders have reduced staff
- Port operations may slow
- Trucking availability reduced
- Book freight early (before CNY rush)
Quality Risks
Pre-CNY rush can affect quality:
- Rushed production = more defects
- Less time for inspection
- Temporary workers before CNY
- Consider enhanced QC for pre-CNY production
Seasonal Inventory Optimization
Optimal seasonal inventory balances service levels against overstock risk.
Initial Buy Strategy
- Core basics: Higher confidence, buy closer to forecasted demand
- Fashion items: Lower confidence, buy conservatively, plan for replenishment
- New styles: Minimal initial buy, test before commitment
Replenishment Strategy
- Reserve production capacity for in-season replenishment
- Pre-position fabric for fast-turn replenishment
- Define replenishment lead time by product
- Set reorder points based on selling velocity
End-of-Season Management
- Week 6-8 of season: Evaluate sell-through, adjust markdown timing
- Clear before next season: Inventory cost of carry vs. deeper discounts
- Carryover candidates: Identify basics that can carry to next year
- Off-price channel: Move excess before it ages further
Carry-Forward Inventory
Some products can carry to next year's same season:
- Basic styles with minimal year-over-year change
- Classic colors and fits
- Products without dated features
Carry-forward reduces markdown losses but requires storage costs.
Metrics to Track
- Sell-through rate by week of season
- Full-price vs. markdown sales mix
- Stockout rate for replenishable items
- End-of-season inventory as % of buy
Building Your Seasonal Calendar
A master calendar aligns all functions around seasonal timelines.
Calendar Components
- Design milestones: Line review, final adoption
- Buy milestones: Initial buy, reorder windows
- Production milestones: Start, completion, ship dates
- Logistics milestones: Booking, sailing, arrival
- Retail milestones: Floor set, promotional events, clearance
Sample Annual Calendar (Spring Season)
| Date | Milestone |
|---|---|
| Prior June | Design finalization |
| Prior July | Initial buy placed |
| Prior August | Production begins |
| Prior October | Production complete, QC |
| Prior November | Ship from origin |
| Prior December | Arrive at retailer DC |
| January | Distribution to stores |
| February | Floor set, selling begins |
| April | Replenishment orders close |
| May | Markdown begins |
| June | Clear remaining inventory |
Cross-Functional Alignment
Ensure all teams work from same calendar:
- Design knows production deadlines
- Buying knows lead time requirements
- Production knows ship date commitments
- Logistics knows volume and timing
- Retail knows arrival dates
Calendar Review Cadence
- Annual: Set calendar for coming year
- Quarterly: Review upcoming season, adjust as needed
- Weekly: Track current season execution